Tishomingo

Tishomingo

Owner

The City of Tishomingo

Architect

Burns McDonnell

Estimate

$11,566,546.87

Size

Features

  • New WTP - Rehabilitate the Existing Raw Water Intake 
  • New Pumps, Electrical Gear, & Canopy
  • Two New Solids Contact Clarifiers
  • New Dual Media Gravity Filters with GAC
  • New Backwash Pumps and Air Scour Blower
  • New Clearwell and High Service Pumps
  • Chemical Storage & Delivery System
  • New Chemical Feed Facilities and Injection Points for Alum, Polymer, Caustic, Hypochlorite, and Orthophosphate
  • New Flow Metering Throughout the WTP
  • New WTP
  • 3k SF Building
  • Sidewalks Around the Plant
  • 300ft of Underground Stormwater
  • 2k Ft of Water Pipline(6"-20") 
  • 750ft of 4" Wastewater Pipeline
  • Duplex Lift Station
  • Portable Water Facilities 

 